Linking a trigger schedule using the Nav tree

Often a trigger schedule is in a different container from the target component container. In this case, the easiest way to link is using the Nav tree.
Prerequisites: You have a trigger schedule
  1. Expand the Nav tree to locate the source trigger schedule, noting its name.
  2. Right-click the trigger schedule and select Link Mark from the popup menu.
  3. Expand the Nav tree to locate the target component.
    (In some cases, the target may be an extension of a point or other component.)
  4. Right-click the target component and select Link From “<target schedule name>” from the popup menu.
    A Link dialog appears.
  5. In the source (left) side of the Link dialog, click the trigger schedule’s Trigger slot.
  6. In the target (right) side of the Link dialog, click the desired action of the target component.
  7. With both source and target sides selected in the Link dialog, click OK.
The target component (point or extension) is now linked to the trigger schedule.